In-water construction continues at the Washington Bridge Rebuild project during daytime hours. Crews are also continuing foundation work for the west abutment.
We are installing 32 drilled shafts that will form the foundation of the new bridge. Each shaft will extend approximately 130 feet to bedrock, creating a support system for the bridge’s piers and abutments. At present, six drilled shafts have been installed and concrete placed inside them. Vibration and noise monitoring as well as erosion control are in place.
Next week, we’ll have alternating lane closures for bridge work on I-95 South at Exit 36A to I-195 East on Monday night, from midnight to 5 a.m., and then Tuesday through Thursday nights from 10 p.m. to 5 a.m.
On Wednesday night, we need to close the right lane on I-195 East, from Exit 2C to the Massachusetts line for drainage structure repairs, from 9 p.m. to 7 a.m.